Siskon - Reference List
Siemens AE, Greece
Client: | Siemens AE, Greece |
Project: | SS 20/110 kV Wind Park Bogdanci, . |
Description: | Turn Key, Substation control and protection system,110kV cabinets, Siprotec 4 devices parametrization, Siemens SICAM PAS and SCC SCADA design, commissioning and SAT |
Realized: | 2013 |
Client: | Siemens AE, Greece |
Project: | LOT 4 - Substation automation of SS Petrovec, SS Skopje4, SS Тetovo1, SS Tetovo2. |
Description: | "Turn-key". Design, assembly and commissioning of control and protection cabinets in substations SS Petrovec, SS Skopje4, SS Тetovo1, SS Tetovo2. |
Realized: | In phase of realization |
Client: | Siemens AE, Greece |
Project: | LOT 4 - Substation automation of SS Petrovec, SS Skopje4, SS Тetovo1, SS Tetovo2. |
Description: | Parametrization of control and protection devices in SS Petrovec, SS Skopje4, SS Тetovo1, SS Tetovo2 and design and putting into operation of local SCADA in SS Petrovec and SSTetovo2. |
Realized: | In phase of realization |
Client: | Siemens AE, Greece |
Project: | Design, Supply and Installation of 400/110 kV S/S Stip, Macedonia for MEPSO (Macedonian transmission system operator), Skopje |
Description: | "Turn-key". Design, assembly and commissioning of Control and Protection cabinets, cabinets for AC and DC supply. SAT of 400kV OHTL Stip. In total 84 control and protectioncabinets. |
Realized: | February 2010 |



Client: | Siemens AE, Greece |
Project: | LOT 3 - Substation automation of SS Dracevo and SS Petrovec. |
Description: | "Turn-key". Design, assembly and commissioning of control and protection cabinets in substation SS Dracevo for EVN Macedonia AD, Skopje. |
Realized: | December 2009 |



Client: | Siemens AE, Greece |
Project: | LOT 3 - Substation automation of SS Dracevo and SS Petrovec. |
Description: | Parameterization of control and protection devices and design and putting into operation of local SCADA in SS Dracevo for EVN Macedonia AD, Skopje. |
Realized: | December 2009 |


Client: | Siemens AE, Greece |
Project: | Design, Supply and Installation OHTL bay in 400/110 kV Dubrovo, Macedonia for MEPSO (Macedonian transmission system operator), Skopje |
Description: | "Turn-key". Design and assembly of Control and Protection cabinets. |
Realized: | September 2008 |
Client: | Siemens AE, Greece |
Project: | Modernization of control, protection and monitoring of substation Tirana 1 and Elbasan 1. |
Description: | Assembly of control and protection cabinets for substations Tirana 1 and Elbasan 1. |
Realized: | April 2008 |